This test is to assess your knowledge in Schedule Management.
Full mark in this test earns you 2% out of the 100% for this course.
You can take this test only ONCE
Pass mark for this test is 60%. if you score less, contact the admin for a retest.
0 of 10 Questions completed
Questions:
You must fill out this field. |
|
You must fill out this field. |
|
You must fill out this field. |
|
You must fill out this field. |
You have already completed the test before. Hence you can not start it again.
Test is loading…
You must sign in or sign up to start the test.
You must first complete the following:
0 of 10 Questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
Average score |
|
Your score |
|
While planning the schedule for your project, you frequently refer to the project calendar. The project calendar is:
As a project manager, you are in the process of preparing the project schedule for the project. Which of the following accurately depicts the sequence of your activities before you began to prepare the project schedule?
After one year of construction, an office building is scheduled for completion on 30 January. The landscaping work needs to start 15 days prior to the building’s completion. Which of the following relationships most likely represents the relationship of the start of landscaping work to the completion of the office building?
George is managing a construction project and currently sequencing the project activities and defining their logical relationships. Two activities have both the SS and FF relationships. How should George schedule these activities?
The accuracy of Activity Duration estimates can be improved by considering the amount of risk in the original estimate. The three types of estimates on which three-point estimates are based are:
Earned Schedule (ES) is an extension to the theory and practice of EVM. Earned schedule theory replaces the schedule variance measures used in traditional EVM with ES and actual time (AT). Using the alternate equation for calculating schedule variance:
Which process is MOST responsible for managing changes to the schedule components of the Project Management Plan?
A technique that iterates the project schedule many times to calculate a distribution of possible project completion dates is:
The critical path method (CPM) calculates the theoretical early start and finish dates and late start and finish dates. The difference between the late and early start of a task is a:
You are managing a project that involves work on a film shoot. The editing activity can happen only after the film is shot. The best description of the logical relationship between the editing and shooting of the film is: